MCL Example - Contractor

MCL – Contractor

HKIE Competence RequirementsRelevant Engineering Contractor Experiences
Applying Mechanical Engineering Knowledge (C1, C2, C11)
C1.Comprehend and apply knowledge of accepted principles underpinning widely applied good practice for professional engineering;
  • Apply appropriate mechanical engineering knowledge and skills to:
    • (i) Develop detail design submissions, including drawings, calculations, method statement, fabrication or manufacturing process, etc., to justify the viability of the design to fulfill specified requirements, including but not limited to system or competent performance, in-situ feasibilities to install and commissioning of cooling system, heating system, ventilation system, piping system, air compressor system, mounting system, hoisting system, control and monitoring system, etc.; or
    • (ii) Prepare and conduct system or component failure incident investigation reports, which cover root cause(s) analysis and respective engineering improvement or rectification suggestions with substantiations, for cooling system, heating system, ventilation system, piping system, air compressor system, mounting system, hoisting system, control and monitoring system, etc.; or
    • (iii) Provide engineering design and professional advice to improve of any existing engineering design or system in enhancing constructability, operability, maintainability, reliability or operation efficiency of cooling system, heating system, ventilation system, piping system, air compressor system, mounting system, hoisting system, control and monitoring system, etc.,
C2.Comprehend and apply knowledge of accepted principles underpinning good practice for professional engineering that is specific to Hong Kong; and
  • Understand and familiarize with statutory requirements such as Factories and Industrial Undertakings Ordinance (Cap. 59) and other ordinances, regulations and code of practices for project experiences in C1;
C11.Maintain the currency of his or her professional engineering knowledge and skills.
  • Organize and attend related CPD activities in accordance with HKIE CPD requirements.
Developing Technical Solution (C3 and C4)
C3.Define, investigate and analyse complex engineering problems in accordance with good practice for professional engineering; and
  • Investigate infrequently encountered complex engineering problems without precedent reference of solutions for cooling system, heating system, ventilation system, piping system, air compressor system, mounting system, hoisting system, control and monitoring system, etc.; and be responsible to resolve the problems with originality in analysis by applying professional knowledge and skills in mechanical engineering and good engineering practices
  • Develop engineering investigation plans and procedures to simulate or generate the problems and collect, organize, analysis relevant information to identify the root cause(s) of complex engineering problem.
C4.Design or develop solutions to complex engineering problems in accordance with good practice for professional engineering.
  • Make use of the analysis results from above and apply relevant mechanical engineering knowledge and skills, and good engineering practices to plan and supervise the development and implementation of solution(s) for cooling system, heating system, ventilation system, piping system, air compressor system, mounting system, hoisting system, control and monitoring system, etc., to address the root causes.
  • Develop engineering solutions shall cover, but not limited to, necessary engineering design details, appropriate manufacturing information, necessary construction and installation methodologies, and system commissioning plan and procedures: (i) for any new engineering system, plant or installation; or (ii) for repairing, reinstating, alternation and improvement of any existing engineering system, plant or installation.
Managing Engineering Work (C5, C6, C7 and C12)
C5.Be responsible for making decisions on part or all of one or more complex engineering activities;
  • Be responsible for the management of new installations and/or modification and/or maintenance of cooling system, heating system, ventilation system, piping system, air compressor system, mounting system, hoisting system, control and monitoring system, etc.
  • Manage the use of diverse resources including people, money, equipment, materials and technologies;
  • Participate the resolution of critical problems arising from interactions among wide-ranging technical, engineering and other issues;
  • Develop methodology statement and coordinated with various interfacing parties for infrequently encountered complex engineering activities.
C6.Manage part or all of one or more complex engineering activities in accordance with good engineering management practice;
  • Supervise the construction works of cooling system, heating system, ventilation system, piping system, air compressor system, mounting system, hoisting system, control and monitoring system, etc. and inspect the quality of the work and to deal with any problems that arise.
  • Carry out extraordinary and emergency maintenance work on cooling system, heating system, ventilation system, piping system, air compressor system, mounting system, hoisting system, control and monitoring system, etc.
C7.Identify, assess and manage engineering risk; and
  • Conduct risk assessment and manage the risks associated with the installation, repair, maintenance and overhaul of the cooling system, heating system, ventilation system, piping system, air compressor system, mounting system, hoisting system, control and monitoring system, etc.
C12.Exercise sound professional engineering judgement.
  • Be responsible for engineering activities requiring judgement in technical, quality, manpower, financial, safety, environment aspects.
Upkeeping Professional Acumen (C8, C9 and C10)
C8.Conduct engineering activities to an ethical standard prescribed by the HKIE;
  • Understand and familiar with HKIE ethical standard and show how to apply them in projects.
C9.Recognize the reasonably foreseeable social, cultural, health, safety, sustainability and environmental effects of professional engineering activities generally;
  • Involve in the application of energy saving systems, development of schemes with reference to climate change, activities related to health and safety regulations, etc.
C10.Communicate clearly with other engineers and others that he or she is likely to deal with in the course of his or her professional engineering activities.
  • Demonstrate the effective communication skills with workers, engineers, stakeholders and public related to design, implementation, operation and maintenance , incidents investigation and providing professional advice on mechanical engineering for cooling system, heating system, ventilation system, piping system, air compressor system, mounting system, hoisting system, control and monitoring system, etc.
Background

i. Periods of Training and Experience

ii. Chronological order, giving inclusive dates in months and years

iii. As details of duties can be found in application form, they may not be repeated in this report.

Training

From

To

Company

Position

1/2015

12/2016

An Engineering Consultant Company

Graduate Trainee

 

 

Projects/Duties

 

 

 

Assist the Engineer to prepare the mechanical system design for [n] nos. of engineering projects.

 

Sub Total : (Months/Years)

2 years

 

Professional Experience

From

To

Company

Position

1/2017

12/2017

An Engineering Consultant Company

Assistant Engineer

1/2018

12/2020

An Engineering Consultant Company

Engineer

 

 

Projects/Duties

 

 

 

Prepare the engineering design for [name] Sewage Treatment Works Upgrading Project (Contract Sum: HKD [cost]M or Construction Cost: HKD [cost]M)

 

 

 

Liaised with client, contractors, government officials, etc. and managed the construction programme and the budget plan for [name] projects, Managed the project team with [n] members
(Contract Sum: HKD [cost]M or Construction Cost: HKD [cost]M)

 

Sub Total (Months/Years)

4 years

 

Professional Experiences

i. state the Applicant’s precise positions have occupied in each case and describe clearly the degree of the Applicant’s responsibility assigned; use the first person (I, me, my) to show Applicant’s personal contribution;

ii. indicate the size and cost of the works; keep in about 3 – 4 projects or works demonstrating all competences;

iii. elaborate on any particular problems encountered and how the Applicant arrived at viable solutions with consideration of options or alternatives;

iv. provide evidence to demonstrate the competences (At most four relevant competences should be quoted at a time)

v. provide evidence or examples of recent work to support their claim of attaining professional status, such as reports, plans, calculations, photographs, etc. as appropriate

Applying Mechanical Engineering KnowledgeCompetence

Project Title: Upgrading of [name] Sewage Treatment Works Project Position: Engineer in charge to prepare the pumping and pipework design

Project Brief: Pumping and Pipework System for transferring different working fluid involved in the [name] sewage treatment plant with handling capacity [n] Minimal Liquid Discharge (MLD)

(Contract Sum: HKD [cost]M or Construction Cost: HKD [cost]M)

Professional Experiences

I was the Engineer in charge of the pumping and pipework system design for the [name] sewage treatment plant with handling capacity [n]MLD.

The pumping and pipework system was designed to transfer fluid to different process tanks in the sewage treatment process. Taking cost, safety and reliability into consideration, I developed an overall pipework layout design with the aid of Piping and Instrumentation Diagram. Then I applied Darcy Weisbach Equation and carried out the hydraulic and headloss calculations to determine the pipework dimension and required head.

With consideration of statutory requirements of Factories and Industrial Undertaking Ordinance (Cap. 59), I designed the installation methods of the pumping and pipework system.

C1 & C2

Maintain Engineering Knowledge

I joined and attended seminars, factory visits, group discussions organized by the HKIE, the Institution of Mechanical Engineers (IMechE), etc. to upkeep my technical knowledge, project management skills, etc. Through the direct discussion with experts in different fields, I obtained up-to-date technical knowledge of the sewage treatment process and relevant technology.

Moreover, I obtained my in-depth knowledge of the treatment process control through my professional experiences on projects. I also developed my knowledge of material science related to mechanical system design of treatment facilities, etc.

C11
Developing Technical SolutionsCompetence

Project Title: Upgrading of [name] Sewage Treatment Works Project Position: Engineer in charge of Deodorization System Design

Project Brief: To design a deodorization (DO) system design for [name] sewage treatment works with handling capacity [n] MLD in remote area.

(Contract Sum: HKD [cost]M or Construction Cost: HKD [cost]M)

Professional Experiences

I was responsible for deodorization system design for [name] sewage treatment works. The DO system was designed to extract foul air from process tanks with three air change per hour (ACH).

Following the Piping and Instrumentation Diagram, I conducted the design calculation and prepared the layout of mechanical equipment. I applied my knowledge of fluid dynamics when I carried out the design calculation to determine the required fan capacity and pipework dimension.

For the type and dimension of filter system, I was responsible to investigate the solution of filter system which was without precedent reference of solutions. I noted that the sewage treatment works had very limited site area available and located in remote area; hence, the design of filter should be optimized to meet the operation needs of this site. I identified the concentration and amount of Hydrogen Sulfide (H2S) in different process stages carefully to ensure the deodorization system could remove the H2S gas to a level that met the discharge requirement and managed the risk associated with H2S gas accumulation. I evaluated the pros and cons of different deodorization technologies and determined to use both biotrickling filters and activated carbon filters for this plant. I recommended that the provision of dehumidifier could provide the foul air with 85% relative humidity and hence a suitable environment for activated carbon media. My design proposal was laminar flow in the air duct with a velocity < 10m/s and at least < 0.4 m/s for DO tank contact time. The design recommendation for this deodorization system was agreed upon by DSD.

C3, C4
Managing Engineering WorkCompetence

Project Title: Maintenance Contract of Sewage Handling Facilities in [location] area

Position and Project Brief: Project engineer to manage and supervise the maintenance activities

(Contract Sum: HKD[cost]M or Construction Cost: HKD [cost]M)

Professional Experiences

I was responsible for managing the contract of providing maintenance service to sewage handling facilities in [location] area. I led [n] workers to complete [n] overhaul works under my supervision. I managed the budget plan and project programme to ensure [name] maintenance works could be completed on schedule. For the budget management, I carefully examined the needs and chose suitable mechanical parts with the most competitive price for the maintenance and overhaul works to save on material costs. For the project programme management, I prepared a Gantt Chart to identify the critical path of each overhaul. I also prepared the work plan, labour arrangement plan, contingency plan for each overhaul to ensure that the works could be completed in a timely manner.

Project Title: Upgrading of [name]Sewage Treatment Works

Position and Project Brief: Engineer in charge of implementing the pumping and pipework system of [name] sewage treatment works with handling capacity [n] MLD.

(Contract Sum: HKD[cost]M or Construction Cost: HKD[cost]M)

Professional Experiences

I was the Engineer in charge of implementing of the pumping and pipework systems of [name] sewage treatment works. I led [n] workers to install the [n] pumps and [length] m-long pipework for the [name] sewage treatment works. Before the commissioning test, I checked the pump alignment and if the pumps could be properly operated. I confirmed that no abnormal vibration or noise was heard in the pump operation. During the commissioning test, I verified that the pump could be properly operated at different motor speeds. I also checked the hydraulic calculation and pumping sizing to verify if they were in line with the actual performance. Hence, with my engineering judgement, I concluded that the performance of pumps was satisfactory.

I conducted risk assessments and managed the risk associated with the implementation of the pumping and pipework systems with careful consideration of opportunities and consequences of potential incidents according to work statements and the sequence of installing the pumps and pipework.

C5,C6
C7